My big project, Finishing the Ward 4 AMICAALL/Nhlangano Town Council Social Center, the PCPP

ITS FINISHED

Peace Corps Partnership Proposal (PCPP) with the Nhlangano Town Council (NTC)


http://swazilandreflections.blogspot.com/2011/01/my-big-project-finishing-ward-4.html

First application draft submitted Feb, 2011
Approved & Funding Begins on PC website May 17th
IT WAS COMPLETELY FUNDED on Sept 8th.
Construction started on Oct 24th.
All exterior construction done by Dec 20th.
Grand Opening Jan 5th, 2012
Round 2 of the Funding arrives in early January.
Interior Only Construction Restarts Jan 16th.
Construction all done Feb 16th (minus a million tiny To Do's)
Project Officially Closed May 4th, 2012

Let the children play, learn & be safe.


As of Aug 25th, 2012, I am no longer a PCV, I am now RPCV (Return Peace Corps Volunteer). This blog is my experience in Swaziland between June of 2010 & Aug of 2012. Enjoy.

Wednesday, October 26, 2011

Social Center Part 6 (More of Bathroom Ready)

So today marks the end of 1/2 of phase #1 of Plan A. Which was finishing the spare room and the bathroom. The Spare room gets painted the next couple of days. And the Bathroom's floor is now completed. Which means we have to put in the sinks, touch ups on the toilets and paint plus Doors & Windows then Phase 1 is done. Confused, we have a plan and making it up as we go at the exact same time.


Floor DONE!!






Khetswe - Social Center Manager
(Although not a part of the construction, this building is her responsibility especially once it is completed)


Still waiting on word from Town Council and moving on to plans that don't involve Doors & Windows.

Rest assured Town Council will hold up there part of the partnership it is just a matter of when. Most of the councilors have come to visit to see the progress.




And some of the local wild life (ie the children who would be going to school in the Social Center and WILL BE. The little one room they school in now is in the background)